Protective Shelter Construction Continues
June 23, 2008

On Saturday, June 21, 2008, Archaeological Protective Shelter foundation work resumed by putting up the walls on the Elk Run Church Site Protective Shelter led by Greg Miller and assisted by several St. Stephen’s Church members. Completion of wall work continued on June 22 but was stopped by a member of the Fauquier County’s Building Inspection Department who was passing by and wanted to see the permits for building the Archaeological Protective Shelter.

During a visit and discussion on June 23, with Fauquier County’s Zoning Office, it was determined that our Protective Shelter would probably be reclassified as a Mini-Museum/Commercial activity and all of the various permissions and approvals would have to be obtained before construction could be resumed.